Target Date |
Compliance Team |
QEP Team |
Comments |
2005 |
|||
January 31, 2005 |
Due date for completed “Institutional Summary Form Prepared for Commission Review” |
|
Completed and Submitted |
January 30-31 |
Orientation for Leadership Team with SACS staff |
|
Completed |
February 18 |
Meeting of College SACS Leadership Team: |
|
Completed |
February 25 |
|
Faculty Meeting |
Completed |
February-March |
Orientation for Compliance Audit Committee (Includes Representatives from:)
|
Focus Group Meetings |
Completed |
March 24 |
Compliance Team Meeting |
|
|
April 15, 29 |
Compliance Team Meetings |
Focus Group Meetings |
Completed |
May 25 |
Compliance Team Meetings |
Discuss potential QEP members, chairperson |
Completed |
June 17 |
Compliance Audit Team meetings – review reports completed to date |
QEP Team Chairperson meets with Leadership Team determines Theme from Focus Group data |
Completed |
July |
Work continues by committee members on assignments |
QEP Team meetings |
Completed |
August 3-5 |
Orientation for Faculty and Staff of New SACS process, Update on QEP Theme |
Announce QEP Theme |
Completed |
September 9, 23 |
Compliance Team Meetings |
QEP Planning Team Meetings |
Completed |
October 6, 20 |
Compliance Team meets |
QEP Planning Team Meetings |
Completed |
Target Date |
Compliance Team |
QEP Team |
Comments |
November 10,30 |
Compliance Team Meetings |
QEP Planning Team Meetings |
Completed |
December 15 |
Final Compliance Audit Report due to the President |
QEP Planning Team Meetings |
Completed |
2006 |
|||
January |
Leadership Team conducts Review of Compliance Audit |
IR office does literature search for QEP, Team begins draft report |
Completed |
February |
Double Check of Audit, Web Site and documentation Links |
Team continues report writing |
Completed |
March 1 |
Final Review of Compliance Audit |
QEP Chair circulates draft of QEP report/proposal to QEP team, Leadership Team |
Completed |
March 15 |
Compliance audit due to SACS |
Review of QEP Report |
Completed |
April |
|
|
|
May 15 – 18, 2006 |
Off-Site Committee Review |
|
|
May 30, 2006 |
Disclosure of Findings of Off-Site Review Committee |
|
|
June 15 |
Focused Report?? |
|
|
July 1 |
|
Submission of names of individuals confirmed to serve as QEP reviewers no later than 8 weeks prior to on-site review
|
|
July 15 |
|
Final QEP Report Due to SACS (six weeks prior to site visit) |
|
August |
|
QEP focus of college in-service |
|
October 10 - 12, 2006 |
On-Site Review Conducted |
|
|
|
|
|
|
2007 |
|||
June 19-21, 2007 |
Review by the Commission on Colleges |
|
|